Quick Facts
Budget
$107.5 million -- includes new construction and specialized fittings and equipment such as acoustical installations for music, sprung floors for dance, museum-standard environmental controls for the gallery, film screens, theatre lights and rigging etc. as well as reconfiguration and renovation of spaces in other University buildings impacted by program relocations to the Accolade Project.
New Space: 33,232 m 2
New Student Spaces: 3,500
| Milestones |
 |
April 14, 2003: announcement of seed funding from the
Government of Ontario (Public Infrastructure Renewal) |
 |
August 28, 2003: design development begun |
 |
October 30, 2003: groundbreaking |
 |
November 25, 2004: 'topping off' ceremony |
 |
September 2005: Accolade West occupancy |
 |
February 2006: Accolade East occupancy |
 |
March 20, 2006: official opening/ribbon-cutting ceremony |
|


|