On April 17, 2021, the construction of the Markham Campus reached a milestone with the pouring of the foundation or “raft slab.” In one continuous pour over a 12-hour period, 225 concrete mixer trucks delivered the entire production of two concrete-mixing plants — pouring 1787m3 of concrete to create a foundation two metres thick.
Source: Stuart Olson
Progress Timeline
March 2022 February 2022 January 2022 December 2021 November 2021 October 2021 September 2021 August 2021 July 2021 June 2021 May 2021 April 2021 March 2021 February 2021 January 2021 December 2020 November 2020 October 2020